Unlike classic indicators focused only on progress, PPC seeks to answer one essential question:
Were the tasks we committed to completing actually finished as planned?
PPC is not used to control or sanction teams.
It is used to understand:
- why some promises are not kept,
- where the system becomes unstable,
- and how to progressively improve project reliability.
Simple definition
PPC measures the percentage of planned tasks that were completed as expected over a given period, usually one week.
The formula is simple:
PPC = \frac{Number\ of\ completed\ tasks}{Number\ of\ planned\ tasks} \times 100
Example:
- 20 planned tasks,
- 16 tasks completed as planned.
The PPC is therefore:
PPC = \frac{16}{20} \times 100 = 80%
PPC therefore measures:
- the quality of preparation,
- system stability,
- and the reliability of operational commitments.
Why it matters
In many projects:
- schedules are updated regularly,
- tasks are moved,
- priorities change,
- and delays gradually become "normal".
The problem is that:
- the schedule eventually loses credibility,
- teams no longer truly believe in commitments,
- and the project mainly operates reactively.
PPC changes this logic.
Instead of asking:
"Are we ahead or behind?"
Lean asks instead:
"Are we able to keep our commitments?"
This nuance is fundamental.
Because a high-performing project is not only a project that "moves forward".
It is a project capable of:
- producing reliably,
- predictably,
- and stably.
PPC then becomes a health indicator for the project system.
Concrete example
On a complex construction site:
- several companies make weekly commitments,
- coordinated around production areas.
At the end of the week:
some planned tasks have not been completed.
Instead of simply "rescheduling", the team collectively analyzes the causes:
- access unavailable,
- missing technical information,
- coactivity conflict,
- delayed delivery,
- late arbitration.
Gradually:
- constraints are better anticipated,
- commitments become more realistic,
- and site stability improves.
PPC then increases not because teams "work more", but because:
the system becomes more reliable.
Common mistakes
Using PPC as an individual control tool
PPC measures the quality of the system, not one person's performance.
Looking for an artificially high PPC
Overly cautious commitments make PPC much less useful.
Ignoring reasons for non-completion
The real value of PPC lies in analyzing gaps.
Considering PPC in isolation
PPC must be interpreted alongside:
- constraints,
- workload,
- flows,
- and operational stability.
Confusing activity with reliable commitment
Multiplying started tasks does not guarantee real project progress.
Indicators to track
PPC generally works with other Lean indicators:
- Weekly PPC
- Reasons for non-completion
- Number of constraints removed
- Commitment reliability
- Waiting time
- Schedule variability
- Number of interruptions
- Milestone adherence
- Rework rate
- Team workload
- Flow stability
The objective is to measure the real capacity of the system to produce reliably and predictably.
Frequently asked questions
What is a "good" PPC?
It depends on the project context, but the main objective remains:
- continuous progress,
- and collective learning.
Does a low PPC mean the teams are poor performers?
No. It often indicates:
- poorly managed constraints,
- unstable flows,
- or an insufficiently prepared system.
Why analyze reasons for non-completion?
Because gaps reveal:
- system weaknesses,
- failing interfaces,
- and recurring constraints.
Does PPC replace classic schedule indicators?
No. It complements traditional indicators by measuring real operational reliability.
Does PPC work only in construction?
No. The principle can be applied to:
- projects,
- engineering,
- services,
- and complex collaborative environments.
Leanfinity offer link
Project reliability / acceleration
Leanfinity supports complex projects in:
- implementing the Last Planner System,
- collaborative steering,
- improving the reliability of commitments,
- and stabilizing operational flows.
Our approach aims to build projects capable of:
- keeping their promises,
- learning quickly,
- and producing sustainable performance.
How it works
Define
Clarify the concept and its role in the operating system.
See
Make flows, constraints, gaps, and interfaces visible.
Act
Turn the principle into concrete routines, decisions, and commitments.
Learn
Measure gaps to improve the system without looking for someone to blame.
PPC is generally used within the Last Planner System.
Teams make realistic commitments
Weekly tasks must be:
Completions are checked
At the end of the period:
each task is analyzed,
and considered:
A partially completed task is not considered done.
The causes of gaps are analyzed
Lean mainly seeks to understand:
Examples:
The system learns
Recurring causes make it possible to:
PPC therefore becomes: